Sudan transport and Demining: WFP briefing on road July 08

Document Actions

Main highlights of report:

• Kaya-Yei road is still in danger of closing due to the rains.
• Au and Goli bridges have had a slight delay due arrangement of security. Parts picked up 10th July, and expected to be complete at the end of the first week in August.
• GoSS second tranche still not received, delaying further contracts such as Juba-Kajo-Keji, Narus-Boma and Airports amongst others.

Attachments
 Modified   Published   Title   Source   Download 
2008-Jul-16 WFP_ Briefing on Roads _July 08.pdf
WFP_ Briefing on Roads _July 08.pdf (WFP_ Briefing on Roads _July 08.pdf - 79.34 Kb)
Source : WFP
Activities : Land
Type of document : Report
Country : SD SDN 736 Sudan, Democratic Republic of the
Publication date 2008-Jul-14
 